Mills Pond Park

Summary

Project Number

P12663

Total Budget

$5,334,500

Current Status

Design

Project Updates

  • Land, tree & utility surveys completed.
  • Geotechnical reports completed.
  • Concept and cost validation completed.
  • Athletic field lighting replacement completed by the City of Fort Lauderdale.
  • 100% design plans submitted for site plan approval.
  • Site plan approval comments received and revisions underway. Bid documents to be completed once comments are addressed.
  • Permitting application preparation is in process.
  • Bidding scheduled to start in July 2023.
  • Construction scheduled to start in October 2023.
  • Construction scheduled to be completed in October 2024.

Concept Plan

Mills Pond Park Concept Plan

Mills Pond Park Gallery