Joseph C. Carter Park

Summary

Project Number

P12633

Total Budget

$13,621,000

Current Status

Design

Potential Grants

  • Florida Recreation Development Assistance (FRDAP) – $200,000
  • Florida Cultural Facilities – $200,000

Project Updates

  • Land, tree & utility surveys completed.
  • Geotechnical reports are in progress.
  • Notice to proceed with design issued in June 2022.
  • Stakeholder meetings held in July 2022.
  • Concept and cost validation completed.
  • 30% schematic submitted in January 2023.
  • 100% design plans schedule to be completed in September 2023.
  • Bidding scheduled to start in November 2023.
  • Construction scheduled to start in March 2024.
  • Construction scheduled to be completed in March 2025.